Retainage withheld = eligible progress billing × agreed retainage rate
Current amount payable = eligible progress billing − retainage withheld
Examples use made-up numbers. Education only, not tax, legal or investment advice.
Example
The setup
Example company: Ridgeline Builders Co. (fictional).
Illustrative example.
Independent fictional scenario: Ridgeline Builders Co. submits a $100,000 eligible progress billing with agreed 5% retainage.
Withholding is $5,000 and the current amount payable is $95,000, assuming no other deductions.
This is not a legal rate recommendation or a change to the series WIP ledger.
Your next step
What would change your next decision after you check this against your own records?
Educational content, not tax, legal, accounting or investment advice.
Questions owners ask
Is retainage a discount?
No. It is withheld payment subject to release conditions, not automatically a reduction in contract price. Disputes or agreed adjustments can change the ultimate amount collectible.
When can Ridgeline collect retainage?
When the applicable contract conditions and legal requirements are satisfied. Do not assume every project releases it at substantial completion or on the same deadline.
Does retainage mean revenue has not been earned?
Not necessarily. Cash payment timing and revenue recognition differ. Evaluate earned revenue under the applicable accounting method and track the withheld balance separately.