Job cost calculator: job cost, margin and bid price

Job costing adds up everything a job really costs, including overhead, so you can see the margin you keep before you bid.

Illustrative example. Enter your own job; empty fields count as $0.00.

Your numbers

Your results

Total job cost

$10,080.00

Includes overhead of $30.00 per labor hour = $1,800.00

Profit

$2,920.00

Margin %

22.46%

Markup on cost %

28.97%

Bid needed for your target margin

Add a target margin %

Email me this result

Guide: Job costing for contractors

Members

What-if scenarios

  • Compare several scenarios side by side
  • See which input moves the result most

Members, opening later this year

Estimates only. Results depend on your inputs.

Formulas

  • Labor = labor hours × loaded cost per hour
  • Overhead rate per labor hour = annual overhead ÷ annual billable hours
  • Overhead applied = overhead rate × the job's labor hours
  • Job cost = materials + labor + subcontractors + equipment + overhead applied
  • Profit = bid − job cost
  • Margin % = profit ÷ bid
  • Markup on cost % = profit ÷ job cost
  • Bid needed for a target margin = job cost ÷ (1 − target margin %)

Worked example

Illustrative example. Numbers are made up to show the math.

Materials $4,200.00; labor 60 hours × $38.00 = $2,280.00; subcontractor $1,500.00; equipment $300.00.

Overhead: $90,000.00 ÷ 3,000 hours = $30.00 per hour × 60 hours = $1,800.00. Job cost is $10,080.00.

A bid of $13,000.00 gives a profit of $2,920.00, a margin of 22.46% and a markup on cost of 28.97%.

How to use it

  1. Enter direct materials, labor hours and loaded cost per hour, subcontractors and equipment.
  2. Enter annual overhead and annual billable hours to apply overhead per labor hour.
  3. Enter your bid, or a target margin % to see the bid you need.

Questions owners ask

What goes into job cost?

Direct materials, labor at its loaded cost per hour, subcontractors, equipment for the job, and a share of overhead applied per labor hour.

How do I calculate an overhead rate per labor hour?

Divide annual overhead by annual billable hours. $90,000.00 ÷ 3,000 hours = $30.00 per labor hour, then multiply by the job's labor hours.

How do I set a bid from the margin I need?

Divide job cost by (1 − target margin %). Choose the target from your own numbers; a bid built from cost plus a markup can land below the margin you need.

More free tools

Sources

No external research cited. Calculations and illustrative assumptions are shown above; this is not evidence of a real owner outcome.

Educational content, not tax, legal or investment advice.

Updated

The Owner Track Letter

One cash decision. One AI workflow.

Tell us about your business (optional)
Newsletter tracks

Privacy · Terms

Membership

Become a founding member.

Membership opens later this year. Join the list to hear first. No payment today.

Join the founding members list →